Department of the Interior

Quicktime Implementation- Phase 2 Employees

 

ID

Task Name

Start

Finish

 

2004

 

Apr  

May

Jun

Jul

Aug

Sep

Oct

Nov

Dec

Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

 

1

MMS, USGS, OS, OIG, SO -Train 13,821 employee

Mon 11/3/03

Mon 3/8/04

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2

  Analysis/Requirements Gathering

Mon 11/3/03

Mon 11/17/03

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

3

  Project Planning and Preparation

Tue 11/18/03

Mon 12/1/03

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

4

  Employee training

Tue 12/2/03

Mon 3/8/04

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

5

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

6

BIA - Train 10,306 employee staff

Tue 1/6/04

Fri 7/30/04

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

7

  Analysis/Requirements Gathering

Tue 1/6/04

Fri 4/16/04

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

8

  Project Planning and Preparation

Mon 4/19/04

Fri 5/14/04

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

9

  Employee training

Mon 5/17/04

Fri 7/30/04

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

10

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

11

NPS - Train 26,620 employee staff

Mon 2/2/04

Thu 9/30/04

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

12

  Analysis/Requirements Gathering

Mon 2/2/04

Fri 4/30/04

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

13

  Project Planning and Preparation

Mon 5/3/04

Fri 5/28/04

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

14

  Employee training

Mon 5/31/04

Thu 9/30/04

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

15

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

16

FWS - Train 8685 employee staff

Wed 3/3/04

Mon 5/31/04

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

17

  Analysis/Requirements Gathering

Wed 3/3/04

Fri 3/12/04

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

18

  Project Planning and Preparation

Mon 3/15/04

Tue 3/30/04

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

19

  Employee training

Mon 4/19/04

Mon 5/31/04

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

20

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

21

BOR, OSM - Train 5739 employee staff

Mon 5/3/04

Fri 7/30/04

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

22

  Analysis/Requirements Gathering

Mon 5/3/04

Fri 5/7/04

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

23

  Project Planning and Preparation

Mon 5/10/04

Fri 6/4/04

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

24

  Employee training

Mon 6/7/04

Fri 7/30/04

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

25

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

26

BLM - Train 13,578 employee staff

Mon 5/3/04

Tue 8/31/04

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

27

  Analysis/Requirements Gathering

Mon 5/3/04

Fri 5/7/04

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

28

  Project Planning and Preparation

Mon 5/10/04

Fri 6/4/04

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

29

  Employee training

Mon 6/7/04

Tue 8/31/04

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Project: Modified Schedule - 04-08-03

Date: Wed 4/9/03

Task

 

Milestone

 

External Tasks

 

 

Split

 

Summary

External Milestone

 

Progress

Project Summary

Deadline

 

Page 1-Attachment 4