Date |
Responsible
Official/Office |
Milestones
DOI |
Bureau
Action Items |
Status/Comments
|
FEBRUARY
|
|
|
|
|
| Week of Feb
3
|
|
|
Bureaus identify
team members for the Cost Structure/ABC Integration Team
|
Completed
|
| Week of
Feb 10
|
|
|
DOI cross-cutting
ABC activities are defined for
Resource Use, Goal 1: energy, non-energy, forage,
forestry, information |
Completed
|
| Feb 21 – May
26 |
LeRon Bielak/OS/PPP
|
Public comment
period for DOI Strategic Plan |
|
Completed
|
| Week of Feb
24 |
|
|
Definition
workshops for all quadrants of Strategic Plan |
Completed
|
| Feb 25 - March
26 |
|
|
ABC Steering
Committee meeting to discuss approach to mapping Activities/Output
to Strategic Plan |
Completed
|
MARCH
|
|
|
|
|
| Week of March
3 |
|
|
Outcome measures
are defined for the Resource Use and Resource Protection quadrants
of the DOI Strategic Plan |
Completed
|
| Week of March
3 |
|
|
ABC Steering
Committee meeting to discuss approach to mapping Activities/Output
to Strategic Plan |
Completed
|
| March 6
|
|
|
Cost Structure/ABC
Integration Team meeting (systems accountants) develops
strategies for:
- Assuring a direct link between
ABC activity code and budget activity
- Least impacting cost structure
for each Bureau
- Consistency among Bureaus where
possible
- Necessary table changes for
each Bureau
- Completing and testing modifications
by August 15
|
Completed
|
| Week of March
10 |
|
|
DOI cross-cutting
ABC activities are defined for the Serving Communities, Resource
Protection, and Resource Use-Goal 2 quadrants of the DOI Strategic
Plan |
Completed
|
| March 14 –
May 19 |
Betty Buxton/BLM
|
|
Begin work
process definitions and development of DOI Goal, Process,
Activity Matrix |
Completed
May 19 |
April
|
|
|
|
|
| Week of April
16 |
Betty Buxton/BLM
Bill Webber/OS/PFM |
|
Cost
Structure/ABC Integration Team completes:
- Identification of cost structure
changes for each Bureau
- Report identifying the changes
each Bureau needs to make
- Briefing on status and issues
for the DAS, Budget and Finance
|
Completed
|
| April 15 –
September 30 |
Lynn McPheeters,
Bob Veltcamp/DOIU
Bureau ABC Training team
|
|
DOI
and Bureaus begin to develop training on how to code time
and purchases to the DOI ABC activities
- Contract w/vendor to develop
ABC training CD
- Complete Dept script
- Schedule Dept/bureau execs
for filming
- Develop training
deployment strategy
|
Bureau
scripts completed 8/15
Contract awarded to Vodium 6/2
Filming for dept/bureau execs
completed 8/19
All filming completed 8/26
Training deployment strategy completed 8/28 |
| Week of April
21 |
USGS, NPS,
BIA, FWS, BOR pilot coordinators |
|
Arizona pilot
is complete. Participating bureaus report out on results
of pilot |
Completed
April 28 |
MAY |
|
|
|
|
| May 9
|
Dave Anderson/OS/PPM
|
e300 for T
& A system submitted to CPIC committee |
|
Completed
|
| Week of May
12
|
Lynn McPheeters,
Bob Veltkamp/DOIU |
|
Lessons learned
from Arizona pilot are incorporated into the training being
developed by DOI and Bureaus |
Completed
5/20 |
| May 19-June
9 |
Dot Sugiyama/OS/PAM
|
|
Bureaus review
draft output, outcome measures, & activity definitions
and provide comments/changes
|
Completed 6/9 |
| May 31
|
Dot Sugiyama/OS/PAM
Kate McKenna/NBC |
Award ABC/M
System contract |
|
Completed
5/30 |
JUNE |
|
|
|
|
| June 3
|
Dot Sugiyama/OS/PAM
Martin Quinlan/NBC |
ABC/M System
Project Management Team meets w/contractor to develop DOI/contractor
project management plan |
|
Completed
6/3. |
| Week of June 9
|
Kit Muller/BLM
|
|
Bureaus/OS review comments
to ABC activity definitions, workload measures, outputs and
develop ABC activity definition set to populate ABC/M system
for Oct 1 |
Workshop held 6/11-12.
Work on activity scrub incomlete. ABC Activity Oversight Team
(AOT) (subcommittee to ABC Steering Committee) to complete
work on activity matrix scrub by 7/23; activity definitions
by 7/31. |
| Week of June 16
|
Bill Webber OS/PFM
Betty Buxton/BLM |
|
Follow-up bureau progress
in cost structure changes. |
Meetings held 6/16-17
with BIA/USGS/FWS/
NPS/BOR. Meetings with MMA/NBC/OSM held week of June 30.
|
| Week of June
25 |
Dot Sugiyama/OS/PMB |
|
Each Bureau
nominates 3 individuals with broad program knowledge to
serve on DOI’s ABC/M Activity Oversight Team (ABC-AOT)
- Tenure on the team will be
3 years and will require approximately 3 weeks per year
|
Completed
– bureau subcommittee of ABC Steering Committee working on
activity scrub from 6/27-7/17 self-nominated as AOT.
|
JULY |
|
|
|
|
| Week of July 1
|
Ron Shepherd/OS/PIR,
Betty Buxton/BLM,
Mike McGreer /OS/PPP, Dot Sugiyama/OS/PAM, Martin Quinlan/OS/NBC
|
Form Configuration
Control Board for ABC/M system |
|
Independent
meetings with CALIBRE have occurred to facilitate design of
ABC/M performance and cost modules. |
| Week of July 8 |
Dot Sugiyama/OS/PAM; Chris Richey/NBC |
Meet with OS Office Directors, OS/Bureau Program
Mgrs and ABC Program Mgrs to discuss coding rules. |
|
Completed 7/17. Series of one-on-one meetings
with OS Office Directors and AOT have occurred between 6/25
- 7/17 to scrub ABC activities. Meetings have generated coding
rules for activities discussed. |
| Week of July 23 |
Dot Sugiyama/OS/PAM |
DOI Goal, Activity
Matrix is completed with buy-in from all the Bureaus |
|
Completed
8/22. Met w/ Scott Cameron and staff to resolve disconnects
between activities and intermediate strategies |
| Week of July 23 |
Bill Webber/OS/PFM |
Cost Structure team is provided
the DOI Goal, Activity Matrix to begin coding cost structure
changes |
|
Bureaus were provided activity
matrix and activity definitions to begin work on 8/10. NPS/FWS
activity definitions still pending. Activity codes provided
9/2-9/8. |
| Week of July 30 |
Dot Sugiyama/OS/PAM;
Bill Webber/OS/PFM; Betty Buston/BLM; Barbara Whitford/NBC |
|
Bureaus provide DOI with a
final crosswalk of Bureau-specific work activities to DOI
crosscutting work activities
- Sum total cost of outputs equals Statement of Net Cost
- Sum total cost of outputs equals the total cost for
the accounting period (cash basis)
- Sum total cost for the accounting period equals the
sum total cost for intermediate outcomes and end outcomes
|
Met w/ bureaus
to review crosswalks 7/30-8/9. Requesting
bureaus provide final crosswalk week of Sep 23. |
AUGUST
|
|
|
|
|
| Week of Aug 6 |
Dot Sugiyama/OS/PAM; CALIBRE |
Define Executive Dashboard
view with Departmental leadership |
|
Administered questionnaire
to MIT subcommittee on Planning, Budget & Financial Integration
for design ideas; solicited input from ABC Steering Committee
on 7/23. Presented mock-up views to DepSec - Budget &
Finance 8/6. |
| Week of Aug
11 |
Betty Buxton/BLM
Bill Webber OS/PFM |
End milestone
for this task. Bureau CFOs are to certify/confirm system
is ready for 10/01/03. |
All
changes (tables, screens, and reports) needed to begin recording
DOI cross-cutting ABC/M activity codes in FFS have been completed
and tested by all Bureaus
- Accounting records
are structured in a manner to ensure that every spending
transaction contains an ABC work activity code (and corresponding
output) that is linked to the budgetary account that is
funding the transaction – all labor and operations
|
Bureaus working progress |
| Week of Aug 15 |
Betty Buxton/BLM |
All output, outcome measures,
and activity definitions are complete and loaded into DOI
work activity database |
|
Activity titles/codes entered
9/8; definitions and measures must be finalized-awaiting input
from NPS/FWS as of 9/8 |
| August 19 |
Tony Garrett/BLM; Dolores Chacon/NBC |
ABC Satellite broadcast with
bureaus |
|
Completed 8/19. Providing bureaus
with copies of taped broadcast. |
| August 20 |
LeRon Bielak/OS/PPP |
|
Bureaus submit five-year targets for
end outcome and intermediate outcome measures in the DOI Strategic
Plan |
|
| Aug 20 - Sept 30 |
Lynn McPheeters, Bob Veltkamp/DOIU; ABC Training
contractor |
Deliver ABC Training |
|
USGS
presented cyberseminar 8/26.
Bureaus
review training on Vodium link 9/3
Edits
due to Vodium 9/8
Bureaus
submit requests for # of CDs needed to DOIU 9/8
Internet
link and CDs available for employee access 9/15 |
| August 31
|
ABC/M System
contractor |
Performance module prototype delivered |
|
|
SEPTEMBER
|
|
|
|
|
| Week of Sep 8 |
Mike McGreer/OS/PPP |
|
DOI/Bureaus complete any needed modifications
to workload and performance systems to accommodate new outputs
and outcome measures |
|
| Week of Sep 15 |
Mike McGreer/OS/PPP |
End outcome and key intermediate strategies
defined for Performance Module |
|
|
| Week of Sep 15 |
Dot Sugiyama/OS/PAM; Chris Richey/NBC;
Betty Buxton/BLM |
Publish ABC/M coding rules |
|
|
| Week Sep 15 |
Mike McGreer/OS/PPP, Dot Sugiyama/OS/PAM
Bureau ABC Program Managers, Performance Management Council |
Form ABC/M System Integrated Test Team |
|
|
| Week Sep 15 |
Mike McGreer/OS/PPP, Dot Sugiyama/OS/PPP,
ABC/M System Integrated Test Team |
Develop test criteria for ABC/M system |
|
|
| September 15
- December 31 |
ABC/M System
Test Team and Users Group, DOI ABC/M Configuration Control
Board |
Test Team
and Users Group test performance module. Performance
module finalized |
|
|
| Week of Sep 15 |
Dot Sugiyama/OS/PAM |
Present completed ABC/M Activity/Goal
matrix showing DOI cross-cutting activities to Asst Secs/Sec
Norton |
|
|
| Sept 22 |
LeRon Bielak/OS/PPP |
|
Remaining intermedieate strategies defined for
performance module |
|
| Week of Sept 30 |
Lynn McPheeters, Bob Beltkamp.DOIU; Bureau ABC
training team |
|
Bureaus develop "pocket tools" to encourage truth
in coding and assist employees in learning and remembering
new ABC activity codes |
|
OCTOBER
|
|
|
|
|
| Week of October
1 |
|
|
Bureaus will
code time to activities into FPPS via paper or front-end system;
|
|
| October 1
|
ABC/M System
contractor |
ABC/M module
prototype delivered |
|
|
| October 1 |
Bing Topper/OS/POB, Bureau ABC Program
Managers |
|
Each Bureau and the OS Budget Office
completes and disseminates a plan for direct charging of
time and purchases by employees
- Employees charged as worked, not as planned
- Adequate procedures and controls are in place
to preclude overspending of accounts
- Central accounts are eliminated or significantly
reduced
- Procedures and controls are in place to
accomodate the purpose of the former central account
|
Bureaus have
included business rules in their ABC training and will be
diseminating coding guidance by 9/30.
QuickTime implementation
has begun across the Dept 8/10.
Ongoing discussion with NBC
Finance to develop systematic approach to preclude overspending
accounts from 8/1.
Will discuss with appropriate
subcommittee staff as change would require congressional
approval. |
| October 1 |
Nina Hatfield/Bureaus/OS Offices |
|
Responsibility for monitoring account
balances is established and included in employee peformance
evaluations.
|
|
| October 1-Debember
31 |
ABC/M System
Test Team and Users Group, DOI ABC/M Configuration Control
Board |
Test Team
and Users Group test ABC/M module. ABC/M module
finalized |
|
|
| October 31
|
ABC/M System
contractor |
Executive
Dashboard prototype delivered |
|
|
NOVEMBER
|
|
|
|
|
| Nov 1 – Jan
15, 2004 |
ABC/M System
Integrated Test Team
DOI ABC/M Configuration Control
Board
|
Test Team
tests Executive Dashboard. Executive Dashboard finalized
|
|
|
| November 30
|
Dennis Locke/NBC
|
Quicktime
Phase I implementation completed |
|
|
DECEMBER
|
|
|
|
|
| Week of Dec 1 |
Betty Buxton/BLM
Dot Sugiyama/OS/PAM |
|
ABC-AOT meets to:
- Discuss the ABC work activity definitions for 2004 and
ensure that each team member has thorough and consistent
understanding of the definitions
- ABC-AOT members will be called upon to assist in
their Bureau's training activities
- Draft a team charter for approval by the Deputy Assistant
Secretaries
- Establish clear change control guidelines and controls
for ABC work activities
- Reviews Bureau activity crosswalks to DOI crosscutting
activities and recommends approval or disapproval to the
Deputy Assistant Secretaries
|
|
| December 31
|
ABC/M System
contractor |
Final Performance
and ABC/M modules delivered |
|
|
JANUARY
|
|
|
|
|
| Week of Jan 10 |
Dot Sugiyama/OS/PAM; Lynn McPheeters/DOIU; ABC/M
System contractor |
Train users/executives on ABC/M system |
|
|
| Week of January 15 |
Pam Haze/OS/POB |
DOI and Bureaus
make final decision regarding how Bureaus and Offices will
fully comply with SFFAS#4 while, at the same time, providing
information necessary for budget and performance integration
- Policy document is issued
|
|
POB is working with BLM and OSM to determine
how they use ABC/M to further budget and performance integration
throughout the 2005 formulation cycle (May - Sep 2003). Initial
guidance on how to use ABC/M for 2006 budet formulation will
be provided in 1st qtr FY04. |
| January 15
|
ABC/M System
contractor |
Final Executive
Dashboard delivered |
|
|